Infiniti QX4 service since 1996 of release
1. Introduction
2. Maintenance instruction
3. Routine maintenance
4. Engine
5. Cooling and heating systems
6. Power supply systems and managements
7. Start and charge systems
8. Transmission line
8.1. 4-step automatic transmission
8.2. Transfer case
8.3. Differentials, power shafts / semi-axis
8.3.1. General information and check of a condition of components
8.3.2. Removal and installation of differentials
8.3.3. Replacement of sealing laying of forward differential
8.3.4. Removal and installation of a connecting flange and replacement of an epiploon of back differential
8.3.5. Removal, service and installation of the oil pump
8.3.6. Removal and installation of back semi-axes
8.4. Driveshafts
9. Brake system
10. Suspension bracket and steering
11. Body
12. Electric equipment
 








8099f600






8-3-2-snyatie-i-ustanovka-differencialov.html

8.3.2. Removal and installation of differentials

 PERFORMANCE ORDER

  1. Remove the forward driveshaft (see. Removal and installation of driveshafts) — at once закупорьте an opening in a transfer case for the purpose of the hit prevention in dirt assembly.
  2. Remove forward section of a transfer case.
  3. Remove a power shaft.
  4. Turn out bolts of fastening of assembly of forward main transfer.
  5. Installation is made upside-down.
  1. In summary fill in in differential assembly necessary amount of lubricant liquid of a demanded grade.


Back differential

 PERFORMANCE ORDER

  1. To Poddomkratta the car also establish it on props (see an illustration the Scheme of an institution of props for car fixing in the lifted situation). Prop up also a case of assembly of the back bridge.
  2. Merge lubricant liquid.
  3. Having marked original landing situation, remove the back driveshaft (see. Removal and installation of driveshafts) — at once закупорьте an opening in a transfer case for the purpose of the hit prevention in dirt assembly.
  4. Remove semi-axes (see. Removal and installation of back semi-axes).
  5. To Otsoyediinta electroconducting from wheel ABS sensors.
  6. Turn out bolts of fastening of differential to a case of the back bridge.
  7. Turn out bolts of fastening of assembly of reverse main gear.
  1. Installation is made upside-down — track correctness of placement of sealing laying.
  1. In summary fill in in differential assembly necessary amount of lubricant liquid of a demanded grade.